PROJECTS
S.No | Particulars | Time line for Implementation | Date(FCC) |
---|---|---|---|
A. |
Announcement of Selected Institutes for Establishment of AICTE IDEA Labs |
Immediately After the Approval |
|
1. |
Issuance of Offer Letter by AICTE |
X day |
10-02-2025 |
2. |
Submission of Acceptance Letter by the Institution |
X+10 days |
20-02-2025 |
3. |
Issuance of Sanction Letter by AICTE |
X+15 days |
25-02-2025 |
4. |
Creation of Separate Bank Account for IDEA Lab and Initiate/Planning for the Procurement process |
X+18 days |
28-02-2025 |
5. |
Participation of Institutions in Orientation Program conducted by AICTE |
Second/Third Week from the date of Issuance of Sanction Order |
11-03-2025 to 18-03-2025 |
6. |
Transfer of Funds (Institute Contribution) by Institution to IDEA Lab Bank Account of Institution |
X+30 days |
12-03-2025 |
7. |
Confirmation of Funds Transfer by Institute on AICTE IDEA Lab Portal |
X+30 to 35 days |
12-03-2025 to 17-03-2025 |
8. |
Transfer of FIRST Installment Funds by AICTE |
X+45 days |
27-03-2025 |
9. |
1st Review of Progress by AICTE |
X+60 days |
11-04-2025 |
10. |
Transfer of SECOND Installment by AICTE |
X+75 days |
26-04-2025 |
11. |
Completion of Procurement by Institutes & Establishment of IDEA lab |
X+90 to 100 days |
01-09-2025 to 10-09-2025 |
12. |
Inauguration of IDEA Lab & Initiation of IDEA Lab Activities |
X+100 to 120 days |
12th September, 2025 |
13. |
Submission of Progress Report by the Institute on IDEA Lab Portal |
X+130 to 135 days |
20-06-2025 to 25-06-2025 |
14. |
2nd Review of Progress by AICTE |
X+135 days |
10-07-2025 |
15. |
Submission of Complete UC (AICTE Amount + Institution Share / Matching Fund) |
X+150 days |
25-07-2025 |
16. |
3rd Review of Progress by AICTE |
X+210 days |
23-09-2025 |
B. |
Withdrawal of Sanction Order/Offer Letter in case of Non-Performing Institutes after the FIRST Review of Progress by AICTE |